Aloom MW50 / Engineering appendix / Screening Rev C
The arithmetic behind the boundary.
This appendix pressure-tests a proposed 50.0 MW facility-input campus boundary. It is screening work—not a detailed design, utility offer, OEM reservation or construction issue.
Declared concept boundary
≤ 50.0 MW facility input
Critical IT
Open
Connection voltage
Open / NSP-selected
Project status
Concept-stage
A01 / Compute reference
A ceiling, not a rack schedule.
The current screening uses NVIDIA GB300 NVL72 and HPE provision references only for conditional rack-side arithmetic inside the 50.0 MW facility-input concept boundary. Final rack count and the complete facility balance remain open pending written OEM configuration and accepted design.
Scenario arithmetic only. Each row conditionally assumes one current rack reference per illustrative C250 accounting allocation. 50 × MW1 = 200 × C250 is an accounting reference—not reserved supply, an accepted rack configuration or a delivered customer system. Bar length shows the stated multiplication and subtraction inside the 50 MW facility-input concept boundary; it is not forecast headroom, spare critical IT, deliverable capacity, a rack schedule, measured demand or accepted allocation.
Conditional one-rack-per-allocation arithmetic. The remainder to the 50 megawatt facility-input concept boundary is not spare critical IT.
Scenario basis
Conditional one-rack-per-allocation arithmetic
Rack-side arithmetic
Arithmetic remainder to 50 MW—not spare IT
Status
NVIDIA published maximum
200 × 142 kW
28.4 MW
21.6 MW
Scenario only
HPE EDPp upstream-provision scenario
200 × 155 kW
31.0 MW
19.0 MW
Scenario only
HPE busway-provision scenario
200 × 192 kW
38.4 MW
11.6 MW
Scenario only
Interpretation The arithmetic remainder to the 50.0 MW facility-input concept boundary must carry fabric, storage, facility systems, electrical and thermal losses, control, house loads and operating margin. It is not forecast headroom, spare critical IT or deliverable capacity. Final rack count remains open.
A02 / Electrical screening
From an open POC to a 33 kV reference campus distribution boundary.
The network service provider selects the point-of-connection voltage and protection basis. The 33 kV A/B arrangement is a study reference only: topology, feeder assignment and operating modes remain open, and no redundancy outcome is declared.
Arithmetic status Power factor, harmonics, ambient derating, step load, fault duty, selectivity, flicker and the NSP offer govern final equipment. The ratings above are screening inputs only.
Point of connection
Voltage, capacity, fault level and protection remain NSP-selected
Queensland screening
Powerlink currently indicates 110/132 kV for 50–150 MW; site-specific and non-binding
Main transformation
Rev C reference: exactly 1 × 60 MVA, 1+0 common source; OLTC and derating open
Campus distribution
33 kV A/B reference; topology, feeder allocation and operating modes open; no N−1 claim
B2 infrastructure
25 × 2 MW accounting allocations using 3.15 MVA equipment references—not a feeder schedule
Rack interface
Accepted local conversion—not raw transmission voltage
A03 / Thermal screening
The full-load duty is campus-scale.
The steady-state heat balance is fixed by physics. Loop temperatures, capture fraction, rejection technology and parasitic power remain site-specific.
Steady-state facility balance
Q̇reject,ss ≈ 50 MWth
Conditional on reaching the full facility-input boundary, excluding transient storage and separately measured energy export.
Water-equivalent flow
ṁ = Q̇loop / (cp ΔT)
Indicative recirculating-flow arithmetic only—not selected pump flow or water consumption.
ALOOM-MW50-M-050 / SCREENING REV C / 2026-08-10
Campus thermal screening boundary
NOT FOR CONSTRUCTION
Illustrative water-equivalent flow scenarios at the 50 MW thermal screening case. Scenario arithmetic only—not selected fluid, pump duty, pipe sizing, water use or measured plant capacity.
Loop ΔT
Mass flow
Water-equivalent volume flow
Status
Loop ΔT10 K
Mass flow≈ 1,196 kg/s
Water-equivalent volume flow≈ 4,306 m³/h
StatusScenario only
Loop ΔT15 K
Mass flow≈ 797 kg/s
Water-equivalent volume flow≈ 2,871 m³/h
StatusScenario only
Loop ΔT20 K
Mass flow≈ 598 kg/s
Water-equivalent volume flow≈ 2,153 m³/h
StatusScenario only
Division scenarios only. Under the ≤50.0 MW facility-input concept cap, 50.0 divided by each illustrative PUE input gives the displayed conditional arithmetic IT ceiling. The PUE inputs are not targets or measurements, and the outputs are not accepted, reserved, available or deliverable critical-IT capacity. Actual facility input, PUE boundary, IT rating, parasitics and operating conditions remain open; no MW50 plant has been built or measured.
MW50 illustrative PUE division sensitivity. Four unmeasured PUE scenario inputs are divided into the 50.0 MW facility-input concept cap. The results are conditional arithmetic ceilings, not targets, measurements or accepted critical-IT capacity.
Illustrative PUE divisor
Facility-input concept cap
Conditional arithmetic IT ceiling
Status
1.10
50.0 MW
45.45 MW
Scenario only
1.15
50.0 MW
43.48 MW
Scenario only
1.20
50.0 MW
41.67 MW
Scenario only
1.25
50.0 MW
40.00 MW
Scenario only
No PUE claim These are division scenarios, not a target, measurement or guarantee. MW50 has no accepted critical-IT rating.
Open duty Design ambient, approach temperature, capture fraction, residual air, fluid chemistry, water, acoustics, plume, redundancy, parasitic power and ride-through remain open.
A04 / Failure domains
No uptime claim before consequence analysis.
Reference grouping creates study boundaries. It does not create resilience automatically. Each shared system needs a declared loss case, operating response and test.
Failure-domain screening only. These rows are reference groupings and open questions—not a selected physical topology, accepted failure analysis or loss case, N+1 design, firm-capacity statement, surviving-output or resilience result, or uptime/SLA claim. A declared loss case, operating response, test and accepted consequence are required.
MW50 failure-domain screening register — Screening Rev C; reference/scenario only, not for construction; consequences remain open.
Domain
Screening posture
Required closure
Status
NSP supply / POC
One commercial-boundary scenario
Firm capacity, outage exposure and any alternate-supply basis require accepted studies and contract terms.
Open
Campus HV
A/B bus scenario
Transfer, protection and maintenance claims require accepted studies.
Open
H10 allocation reference
5 × 10 MW facility-input accounting allocations
This is not a physical feeder schedule; fault containment and surviving useful output remain open.
Accounting reference / open
B2 allocation reference
25 × 2 MW facility-input accounting allocations
The 3.15 MVA equipment reference does not create deliverable campus capacity; workload recovery remains open.
Accounting reference / open
Shared thermal plant
N+1 study input · not a design
Module, pump, control and ride-through requirements follow the accepted duty.
Open
Data + control
Logical-isolation study posture · not a current implementation
Quorum, durable copies, ingress diversity and recovery objectives require service design.
Open
Next / Project development
Replace scenarios with accepted inputs.
A real site study starts with the grid position, site constraints, workload and availability consequence—not a preselected rack count.